Toll Free
GeoTechnicalCellular
SocialTwist Tell-a-Friend 
Application:  Pervious Load Reducing Fill
Product:  Geofill LD Pervious
Owner:  City of New York
Installed:  17,500 Cubic Yards


In July 2006, initial construction of the new Mets Stadium was underway in the parking lot beyond the old stadium’s left-field. The design called for the playing field to be elevated five to six feet above the grade of the old parking lot. However, the additional fill required to accommodate the design would add an estimated 700 pounds per square foot which was problematic because the extra weight would cause substantial settlement of the weak native soils in the area and require a lengthy surcharge of soils until the settlement subsided.

Most proposed solutions to this situation were cost and time prohibitive. The initial plan called for reducing the load on the underlying soils by using Lightweight Aggregate as fill. This would have yielded a density of ~55 PCF after compaction. However, when the owners learned MixOnSite's Geofill LD Low Density Cellular Concrete was being used on a cross-town rival's new stadium, they decided to investigate further.

After further review, the decision was made to use Geofill LD Pervious averaging 29 PCF and 80 PSI. This decision resulted in a direct savings of more than $500,000.00 along with an immeasurable savings of time. The only condition was that the Geofill LD Pervious be as free draining as lightweight aggregate since the infield lacked the drainage system needed
to accommodate a non-pervious material. This challenge was easily met using MixOnSite's Geofill LD Pervious material.

More than 1,000 cubic yards of Geofill LD Pervious was produced per shift using MixOnSite's high capacity dry mix equipment which allowed us to complete our scope of work well ahead of schedule.
News & PressView All
Mixonsite utilized a Geofill Hybrid material containing anti-washout admixtures to fill an abandoned ash pit at the Consolidated Edison site in Brooklyn, NY. Free water within the pit was removed during placement to maintain the specified pit water level.
 
MixOnSite pumped Geofill LD cellular concrete material nearly 3 miles at Brightwater East tunnel project. Material produced on site with high production equipment featuring colloidal mixers.
 
MixOnSite recently developed an innovative foam product to transport solid materials such as mine tailings or waste crusher sands through a pipeline.